The operation of the Ferroalloy-1 high-voltage line has been restored at the Zaporizhia NPP
- Новости
- World
- The operation of the Ferroalloy-1 high-voltage line has been restored at the Zaporizhia NPP
Last night, the work of the Ferroalloy-1 high-voltage line was restored at the Zaporizhia nuclear Power Plant. The power supply to the station is now provided again via two lines. This was reported on March 6 in the Telegram channel of the NPP.
"Last night, the performance of the Ferroalloy-1 high-voltage line was restored at the Zaporizhia NPP. The power supply to the plant's own needs is now provided again via two lines, which is an important factor for ensuring nuclear safety," the report says.
It is noted that the restoration of the second power supply line guarantees stable operation of the cooling systems, which minimizes the risks associated with nuclear and radiation safety at the plant.
The Ferroalloy-1 line was shut down on February 10 due to fire from Ukrainian forces. Then it was reported about the damaged main pipeline of the heating main, which was responsible for supplying heat to residential buildings and social facilities. Later, on February 27, Rosatom CEO Alexey Likhachev noted that a local silence regime had been established at the NPP in connection with the repair work at Ferroalloy-1.
On March 2, Grossi, commenting on the situation at the NPP, called it extremely difficult. He also said that representatives of the IAEA were on the territory of all the nearest nuclear power plants, where they monitored the safety and reliability of facilities.