Fuel filter: Cabinet of Ministers did not support the pipeline project to the Far East
- Статьи
- Economy
- Fuel filter: Cabinet of Ministers did not support the pipeline project to the Far East
The government did not support the idea of building a giant oil pipeline from Omsk to the Far East. It was supposed to solve the region's fuel supply problem, unload the railway tracks for coal transportation and allow for increased supplies to the Asia-Pacific countries. However, regulators considered that the capacity of the Omsk refinery would not be enough for this and it was necessary to extend the pipe to the West. Industry experts believe that the project is of a strategic nature, they considered the arguments of the Ministry of Energy groundless, since Russian refineries located east of Omsk could join the pipe.
Pipeline for oil products from Omsk to the Far East
The Ministry of Energy has worked out the issue of building an oil product pipeline from the Omsk Oil Refinery to the Far East and concluded that the project is currently "not being considered for implementation." This is stated in the materials of the department, which were reviewed by Izvestia.
At the end of February 2025, at a round table dedicated to improving the supply of petroleum products to the domestic market, Deputy Chairman of the Federation Council Committee on Economic Policy Yuri Fedorov announced the need to build a new product pipeline connecting Omsk with the Far East. It was supposed to connect all the eastern refineries to this pipeline system, which would reduce energy risks and relieve Russian Railways.
As noted in a letter from Energy Minister Sergei Tsivilev addressed to Chairman of the State Duma Committee on Energy Nikolai Shulginov (available to Izvestia), according to PJSC Transneft, the implementation of this project will require the construction of more than 7 thousand km of pipeline, as well as a terminal for transshipment of petroleum products to sea transport. The capital cost of the project will amount to at least 1 trillion rubles.
At the same time, over the past five years, there has been an underutilization of the refining capacities of the eastern group of refineries (Achinsky, Angarsky, Khabarovsk, Komsomolsky), given the possibility of increasing oil supplies by pipeline.
The Ministry of Energy believes that "an increase in the supply of petroleum products to the market of the eastern regions of the Russian Federation can be achieved by increasing the volume of oil refining at these refineries."
— Currently, Russian oil companies supply petroleum products to the Asia-Pacific countries in insignificant volumes, and therefore the production volumes of the Omsk Refinery will not be sufficient to form an export resource base for the construction of an oil product pipeline, which will require an increase in the length of this route in the western direction. Considering the above, the project for the construction of the main oil product pipeline in the direction of the Pacific Ocean is currently not being considered for implementation," Sergey Tsivilev's letter says, despite the fact that the capacity of the pipeline itself is not disclosed.
According to a source familiar with the discussion of the project, it was assumed that the costs of the project would be borne by Transneft, including bank loans.
The Ministry of Energy and Transneft did not respond to a request from Izvestia. Senator Yuri Fedorov's office was unable to provide an immediate comment.
Which refineries can connect to the pipeline
In turn, experts believe that the issue of the implementation of this project requires serious work. According to Dmitry Gusev, Deputy Chairman of the Supervisory Board of the Reliable Partner Association, the decision taken is completely unjustified.
— First of all, we have not seen a justification for why this project is estimated at 1 trillion rubles. Secondly, the critical mistake of regulators' justifications is that if the oil product pipeline starts from the Omsk refinery, this does not mean that the pipe will be filled with only the products of this plant," he said.
The expert recalled that along the route there are Achinsk, Angarsk refineries, as well as Khabarovsk, which intends to increase its capacity by building a second stage of the plant with a capacity of up to 10 million tons. There is also the Komsomolsk Refinery, Novy Potok and many small refineries.
— Salavat (Gazprom Neftekhim Salavat) can also connect to the pipe. — Izvestia) and to pump products in an easterly direction. In addition, this product pipeline may reach Kemerovo, where it is worthwhile to place a production facility for the synthesis of fuel from coal and also supply it to this pipeline. Therefore, the base is sufficient and there is no need to further expand the pipeline to the West. I think that there is a substitution of concepts and a lack of elaboration of the issue," Dmitry Gusev believes.
As Izvestia wrote, the Far East is experiencing a serious shortage of petroleum products — with consumption of about 6 million tons per year, its own production is about 4 million tons. That is, about 2 million tons per year have to be imported from Siberia and Central Russia.
In addition, experts believe that these investments will be justified, among other things, thanks to coal companies, which will have the opportunity to increase the supply of their products to the east by unloading Russian Railways. The coal industry ended last year with a consolidated loss of 112.6 billion rubles. Among the reasons are falling global prices for solid fuels, sanctions, expensive logistics and "limited opportunities" for export through the Eastern landfill.
In 2024, according to Russian Railways, about 100 million tons of coal were exported eastward. The strategy for the development of the mineral resource base of the Russian Federation until 2050 states that the total volume of coal shipments through the Eastern Landfill may grow to 121.7 million tons by 2025, to 178.7 million tons by 2030, and to 267.2 million tons by 2035.
—In 2023 and 2024, there were problems with logistics, the railways did not fully cope with the rhythm and uniformity of supplies in the fuel market, as well as with the growing volume of wagons connected to the railway network," said Senator Yuri Fedorov at a meeting in the Federation Council.
According to Ekaterina Kosareva, Managing partner of VMT Consult, the shortage of railway capacity in the eastern direction will only increase.
— If the pipeline construction project is implemented, it will relieve Russian Railways, increase the export opportunities of both coal miners and oil companies, and lower prices for petroleum products in the Far Eastern regions. The cost of shipping products by rail is 3-4 times more expensive than by pipe," she noted.
Gazprom Neft, Rosneft, Lukoil, and Surgutneftegaz did not respond to requests from Izvestia.
What conditions are needed for the construction of the pipeline
The construction of an oil product pipeline can be justified by synchronizing the increase in diesel fuel production as part of the refinery modernization program, connecting a number of plants located in Siberia and the Far East to a new oil product pipeline, and building a long-term strategy to increase export supplies of petroleum products. This opinion is shared by Tamara Safonova, CEO of the Independent Analytical Agency of the Oil and Gas Sector (NAANS-MEDIA LLC).
At the same time, according to her, China and India are now the main consumers of Russian oil, have their own refining facilities and are interested in obtaining margins for processing Russian oil on their territory.
"However, in my opinion, the formation of value chains in Russia is strategically important," Tamara Safonova noted.
According to the agency's calculations, enterprises located east of Omsk — Angarsk NHK JSC, Achinsk Refinery VNK JSC, RN-Komsomolsk Refinery LLC, NOC-Khabarovsk Refinery JSC, Yaysky Refinery (a branch of Neftekhimservice JSC) — may increase volumes by 2030. diesel fuel production is 12.5 million tons, subject to the implementation of the refinery modernization program in the previously planned volumes.
— The Eastern Siberia – Pacific Ocean and Power of Siberia pipeline projects are working like clockwork and are in high demand. At the same time, to ensure the effectiveness of the oil product pipeline project and avoid underloading, it is necessary to conduct an inventory of the refinery modernization program and conclude preventive long—term fuel sales agreements with potential buyers," she added.
According to experts, it is possible that the project was simply frozen until "better times."
— If we assume that Transneft should have taken over the financing, then it is difficult to implement the project at the current rate of the Central Bank. Serious government support is needed here," Ekaterina Kosareva believes.
Recall that in 2024, the State Duma Budget Committee approved an increase in the income tax of Transneft by 40%, after which Transneft proposed to additionally index the tariff for oil transportation by 8.7% — without this, the monopoly expects a shortage of funds in 2027 against the background of a double increase in income tax and an increase in the lack of liquidity to 582 billion rubles by the end of 2029. In December last year, the Federal Antimonopoly Service approved an increase in Transneft's tariffs for pumping oil through main pipelines by 5.79% from 2025.
According to Yuri Stankevich, deputy chairman of the State Duma Committee on Energy, the lack of management decisions on the oil product pipeline project from the European part or the center of Russia to the Far East is explained by the low investment opportunities of state-owned companies and limited resources of the budget system in modern conditions.
The MP noted that pipeline transport has a number of indisputable advantages, including excellent productivity, continuity of work, automation of processes, minimal wear of equipment, relatively low costs of delivering products while maintaining consistent quality.
But on the scale of Russia, the pipeline system is a lifesaver, a guarantee of economic and energy security, and the variability of export supplies depending on price or geopolitical conditions.
High capital investments constrain decision-making at the current moment, priorities are different. But I am sure that the construction is necessary, including to relieve the load from the railway, concluded the interlocutor of Izvestia.