The heating season in the north of the Amur region was in danger of disruption
In the Amur region, a critical shortage of fuel was recorded in the Selemdzhinsky district. They prevent the threat of disruption of the heating season.
The prosecutor's office has filed a lawsuit against the resource supply company LLC MP Soyuz EdAl, which uses the municipal boiler house in the village of Ogodzha. The Blagoveshchensk City Court satisfied the claim and ordered the company to urgently create a reserve of coal at the boiler house.
The concession agreement states that the company is obliged to ensure an uninterrupted supply of heat to residents. However, during a winter readiness check conducted in September, it turned out that there was a catastrophic shortage of coal in the boiler room. So, with a standard stock of 509 tons, there were only 51 tons in the warehouse, which is 3% of the required minimum. Moreover, the volume of fuel has not changed for three weeks, writes IA PriamurMedia with reference to the press service of the vessels of the region.
The company's representative did not challenge the claims in court. He said that the coal is in a remote warehouse of the mine, it is delivered as needed, and the standard will be met. The Court considered this position unacceptable.
The court's decision says that working with such a minimal supply of fuel is a direct threat to people's lives and health, they are deprived of the right to quality public services.
At the end of September, it was reported about the beginning of the heating season in the southern regions of the Amur region. The reason is a steady decrease in the average daily temperature.