The renovation of three schools is planned to be completed in Lipetsk by the end of the year.
- Новости
- Local news
- The renovation of three schools is planned to be completed in Lipetsk by the end of the year.
In Lipetsk, major repairs of schools No. 21, 48 and 77 are planned to be completed by the end of 2026. Mayor Mikhail Shcherbakov told about this on his page on the VKontakte social network.
The work in school building No. 48 is almost completed, the construction readiness is 87%. The contractor renovated the roof, put the interior and engineering networks in order. The renovation also affected the assembly and sports halls, the dining room.
A large-scale renovation of almost the entire building was planned at school No. 77. According to GOROD48, the main part of the work has been completed, the workers are engaged in finishing. Meanwhile, the mayor expressed concern about the pace of repairs and instructed to strengthen the brigade.
Shcherbakov visited these two schools with an inspection, but noted that school No. 21 should also complete repairs by the end of the year. The educational process in the three educational institutions is planned to resume after the winter holidays.
In September, it was reported that four more educational institutions of the regional capital are scheduled to be renovated in 2027. We are talking about school No. 7, 42, 62 and the second building of the 70th.