St. Petersburg assessed the progress of the construction of the Tsymbalinsky overpass
- Новости
- Local news
- St. Petersburg assessed the progress of the construction of the Tsymbalinsky overpass
The construction of the Tsymbalinsky overpass continues in St. Petersburg. At the moment, the readiness of the facility is about 70%, the press service of the city administration reports.
Workers have almost completely pushed the metal structures of both directions over the railway tracks. They are now lowering the supports to the left. About 4.2 thousand tons of steel structures of 5.2 thousand tons of spans were installed.
The road workers also completed work at the exit to Tsymbalina Street, writes 78.ru . They built a retaining wall 12 m high and poured 25 thousand cubic meters of sand.
The lower layers of the roadway on this section have already been prepared. To protect the road from deformations on an area of 36 thousand square meters. m, the builders laid a strong top layer of 570 tons of asphalt concrete.
Earlier it was reported that the general public was shown the tracks of the high-speed highway between Moscow and St. Petersburg. In the Leningrad region, testing of a site built specifically to test all systems has begun.