Ulan-Ude received 80 million rubles for the repair of power lines
Ulan-Ude received about 80 million rubles for the repair of power grids in 2026. "The money" came from "Buryatenergo", a branch of "Rosseti Siberia". Funding for the program has increased by 40%, the work has been completed by 83% and is being implemented strictly on schedule.
"All the necessary materials for repairs are available, there are no risks of non—fulfillment of the program — we will complete the remaining work by the end of the year," said Viktor Perelygin, chief engineer of the branch, quoted by IA UlanMedia.
13.3 km of overhead power transmission lines have already been repaired. 203 out of 250 planned supports were replaced, and another 10.5 km of uninsulated wire was used for self-supporting insulated wire (SIP).
The cable lines were put in order for 4.1 km out of 4.9 km. The equipment was updated at 50 of the 56 facilities — transformer and distribution substations, distribution points.
Next year, 2027, the scale will grow. There are plans to repair 20.5 km of power lines (+54%), 6 km of cable lines (+22%) and equipment at 57 sites. The program has already been sent to the Property Management Committee of the city administration.
Earlier it was reported that in Ulan-Ude, before the rainy season, sewage began to be cleaned daily, which quickly becomes clogged with sand after heavy rainfall. There are almost 40 km of networks in the area of responsibility of utilities.