The AI ran into an energy block. Who will win, who will lose
The main thing in the material:
- Data centers have requested huge amounts of capacity from American energy companies: connection requests exceed 700 GW, which is 10 times more than all US data centers consume today.
- Some of this demand exists only on paper. Texas and other states have begun to review projects and tighten connection conditions to separate real data centers from "phantom" ones.
- The speed of data center construction is outpacing the capabilities of the energy industry. New power grids have been under construction for years, and gas turbines from major manufacturers have already been ordered for several years in advance.
- Big Tech is forced to solve the problem of energy supply itself. Companies are putting data centers next to new power plants and investing in their own energy sources.
- The shortage of megawatts contributes to a greater concentration of the AI market. The largest companies can provide data centers with electricity and equipment in advance, while new projects are becoming more expensive for small players.
The American AI boom is faced with a shortage of electrical power — data centers are being built faster than the infrastructure for their energy supply. As a result, technology companies are forced to solve the problems of shortage of generation and power equipment themselves. Thus, Elon Musk's SpaceX is going to produce gas turbine components in order to shorten their delivery time, since the capacities of the largest manufacturers are reserved until the end of the decade. Continuing the previous discussion about why electricity is becoming one of the key resources of the era of artificial intelligence, "Izvestia" figured out whether the AI race has hit the energy ceiling, whether the United States is facing a nationwide blackout and who will pay the bills.
474 GW in the queue for electricity
The energy industry does not have time to provide American AI data centers with capacity. Tech companies claim huge electricity needs — Reuters estimates that in some regions of the United States, applications from large consumers, mainly data centers, exceed 700 GW. This is more than 10 times higher than the current consumption of American data centers. At the same time, some of the demand may turn out to be phantom: projects exist on paper, but, for example, may not have financing. This makes it more difficult to plan the development of the energy system. There is a risk of either building insufficient capacity and jeopardizing the reliability of the network, or creating redundant infrastructure, the costs of which will ultimately fall on ordinary consumers.
The problem turned out to be so large-scale that the states began to change the rules of connection. Texas became the first major data center location to suspend new connections and begin checking projects. Since 2023, applications from data centers and other large consumers for network connectivity in this state have increased from 48 GW to 474 GW. This is five times the record peak load of the entire Texas power grid. And the experience of other states has already shown how much the stated demand may differ from the real one. For example, the energy company Exelon (based in Chicago), after tightening financial requirements for projects, reduced the estimate of highly probable demand from data centers by about 40%, to 11 GW.
In Pennsylvania, where they also began to apply a more stringent approach, out of more than 100 data center projects, only 20 were eventually granted the necessary permits for further implementation. In Ohio, the stated demand for power has more than halved after the state introduced a fee of up to $100,000 in 2025 for a study on the possibility of connecting large data centers to the power grid.
The exact number of data centers in Texas is unknown: neither the state nor the federal authorities maintain a single database of such facilities. The Texas Tribune counted at least 335 active data centers.
Even after the dropout of "phantom" projects, the real demand remains huge. According to S&P Global, in 2025, the total load of data centers on the energy system reached 64 GW, almost three times the level of 2020. By 2030, this figure may rise to 183 GW.
But it is important to evaluate not only the requested capacity, but also the amount of energy that will be required for the operation of data centers. The International Energy Agency expects that in 2026-2030, electricity consumption in the United States will grow by more than 420 TWh, with about half of this increase coming from data centers. According to Berkeley Lab's baseline forecast, by 2030, data centers will account for about 650 TWh per year - almost 12% of total electricity consumption in the United States.
Such growth rates are changing the entire market: it is no longer enough for a developer to have land, capital and a client — you need to understand whether there is available capacity at a selected point in the network and when it can be obtained. And then there is a new shortage — time. A new data center can be built in 1-3 years, while the creation of the necessary energy infrastructure takes much longer - 5-15 years.
Energy cannot be scaled like servers
The development of data centers is changing the structure of the American generation. According to S&P Global, in June of this year, power plant projects with a total capacity of 1.74 TWh were in the queue for connection to the US energy systems. At the same time, the share of projects in the field of renewable energy and energy storage systems is decreasing, while in the field of gas generation, on the contrary, it is growing. One of the main reasons for this reversal was precisely the increase in the number of energy-intensive data centers: gas is considered as a source of reliable power capable of providing a rapidly growing load. One of the forecasts of analysts from Wood Mackenzie says that to cover the needs of large data centers, it will be necessary to increase gas capacity by 16.4 GW annually until 2035. At the same time, in 2023-2025, only 4 GW per year were commissioned in the country.
Energy companies are already trying to catch up with demand. Last year, gas turbines with a combined capacity of 51 GW were ordered, the highest figure since 2000. In the first quarter of 2026 alone, orders were placed for another 18 GW. Prior to the current cycle, the annual volume of orders for a long time did not exceed 11 GW. The main suppliers of the equipment are GE Vernova, Siemens Energy and Mitsubishi Power. According to the Financial Times, it is almost impossible to buy turbines from them before 2030.
By the end of the second quarter, GE Vernova had received orders and reserved production slots for gas equipment with a total capacity of 116 GW. This figure is expected to reach 125 GW by the end of 2026. At the same time, the company is only now bringing the annual output of turbines to about 20 GW, and plans to increase it to 24 GW in 2028 and to 30 GW by 2030.
The main limitation for increasing production at Siemens is the difficulties with the production of blades and other elements of gas turbines. To partially solve the problem of lack of equipment, Elon Musk's SpaceX intends to independently produce some components of the turbines, hoping to shorten their launch time by a maximum of 18 months. This is of particular importance for SpaceX, as the company has become a major AI infrastructure operator and receives income from leasing its computing power to other companies. Delays in the supply of energy equipment directly limit the expansion of this business.
In fact, the AI boom is starting to affect the entire industrial chain. To connect a new power plant and a large consumer, power transformers, switchgear and other equipment are needed. The problem is particularly acute with transformers, which have a delivery time of up to five years. Production cannot be increased quickly, so the United States remains dependent on imports of electrical components, including from China. Nevertheless, the growing demand for energy equipment is forcing manufacturers to expand their capacities, launching a new investment cycle in the industry.
Will the network survive and who will pay the bill
When new large consumers are connected to the grid (even if there is enough capacity), the question inevitably arises about the reliability of the power system, which must withstand peaks in demand and load fluctuations. The risk is not hypothetical. In 2024, 60 data centers in Virginia were simultaneously disconnected from the grid after a minor malfunction, which, according to experts, almost led to the collapse of the entire power grid. In other words, data centers are becoming such large consumers that they can affect the stability of the network not only by increasing the load, but also by its abrupt disappearance. Such imbalances can trigger a cascade of accidents and outages, but it is premature to say that the development of AI will lead to a nationwide blackout.
The operators plan to invest $100 billion in the development of the electric grid infrastructure. This does not mean that all investments are related to data centers, but it is their rapidly growing demand that forces the acceleration of some network projects. At the same time, the costs of such infrastructure are traditionally distributed among a wide range of consumers, that is, not only between data centers. Analysts at Wood Mackenzie warn that if these rules are not changed, some of the costs will fall on the shoulders of American households and businesses. There are also concerns about future price increases for electricity itself. Analysts say that the construction of new generating capacities will be economically attractive with an increase in the cost of electricity. And then all consumers will feel the effect. That is, the entire population will pay for the AI boom.
Therefore, in the same Texas, the governor is promoting an initiative so that data centers themselves pay for the electrical infrastructure necessary for their operation. And in July, New York State imposed a moratorium on the construction of hyperscale data centers. They intend to oblige data centers to either pay more for electricity or provide additional generation.
As a result, the problem has spread to the federal level. The Energy Regulatory Commission (FERC) has required six regional network operators to either justify the current tariffs and rules for servicing large consumers, including data centers, or change them. The regulator seeks faster connection of such facilities, but at the same time requires to ensure the reliability of the network and the affordability of electricity for Americans.
Access to electricity is becoming one of the factors of competition between the largest technology companies. According to The Wall Street Journal, Amazon data centers in the United States consume up to 9 GW of power (about the same amount is the generating capacity of all of North Dakota), Microsoft and Google - about 5 GW each, Meta (recognized as an extremist organization and banned in the Russian Federation) — about 4 GW.
The development of artificial intelligence is unlikely to stop due to lack of electricity, but each new project will face more and more obstacles, and the next unit of computing power will cost more. If data centers are obligated to independently provide the additional generation they need and pay for the network infrastructure, the structure of their capital expenditures will change: energy supply will cease to be an operational issue and will become part of the data center project itself. The largest technology companies will be able to overcome this barrier more easily than their small competitors, which means that the concentration of the AI market will increase.
As a result, the winner is the one who has already secured access to key elements of the scarce energy infrastructure: a working power plant, a site with a confirmed connection, and power equipment. This is where the new frontier of the AI race lies: between those who can secure the next megawatt and those who will have to wait for it for years, and it is not known at what price.