Water shutdown postponed in Krasnoyarsk due to heavy rains

0
Озвучить текст
Select important
On
Off

Krasnoyarsk has changed its winter preparation schedule. It was decided to postpone the planned shutdown of the Kazachy Island and Gremyachy Log water intakes to a later date. It was supposed to take place from August 7-9.

The reason for the postponement was abnormal heavy rains, which led to flooding of construction pits and trenches at engineering network modernization facilities. Comprehensive repairs are combined with work on connecting new networks.

Forecasters predict heavy rains and thunderstorms during the previously scheduled shutdown days.

According to KrasnoyarskMedia news agency, with reference to KrasKom, the decision was made at the request of construction contractors. They complained that they did not have time to complete the preparatory excavation work by the scheduled date.

According to Oleg Goncherov, General Director of KrasKom, it is extremely inefficient to start stopping water intakes at a time when construction sites are flooded. This may lead to a delay in the timing of water shutdowns for residents.

The developers will approve the new dates of work together with the city administration.

On July 29, a significant rise in four rivers was recorded in the Krasnoyarsk Territory — the Us, Oya, Kebezh and Kazyr. During the day, the water level rose from 30 to 130 cm due to heavy rains. On the Kebezh River near the village of Grigoryevka, the water level reached 258 cm at a dangerous mark of 310 cm. The water has reached the floodplain.