Bureyskaya HPP prepared for flooding
In the Amur region, the Bureyskaya HPP is operating normally, but specialists have strengthened control over the hydrological situation in the basin of the Bureysky reservoir and the Bureya River.
The reason is an increase in the water level in the upper reaches of the hydroelectric power station. Over the past day, he has gained 9 cm, writes IA PriamurMedia with reference to the press service of the hydroelectric power plant.
The Far Eastern UGMS predicts that in August the inflow of water to the Bureyskoye reservoir will range from 2000-2500 m3/s, which exceeds the norm.
The Amur Basin Water Management has decided to increase the average daily water consumption through the hydroelectric plant to 900±950 m3/s from August 1. This corresponds to the usual operating conditions of the station, and the opening of the operational spillway gates is not required. In the future, the station will operate depending on the actual hydrological situation.
Thus, the agency writes, the hydraulic structures of the Bureyskaya and Nizhne-Bureyskaya HPPs are prepared to operate in conditions of high water content.
In mid-June, five regions of the country faced a high risk of flooding, and in two dozen more, the effects of bad weather have already manifested themselves in the form of heavy rain floods.